We're one step closer to launch!  The preproduction Myro:Air PCB's should be arriving this week.  If everything checks out we should be on our way... check back for photos of the boards  ;D
Last Edit: March 28, 2014, 03:24:55 PM by Myro Control

Boards arrive today!

Boards in hand -- waiting for a few more components before powering it up.

Here is a sneak peak at the boards working -- you can see some modifications made  :-[

Rev 2 boards scheduled to arrive this week!


Our first batch of pre-production cases have shipped and should be arriving this week!  If everything checks out -- we will drop them off at the silk-screener to get the back panel markings printed, then off to certification.   If everything goes as planned, we're in the home stretch...

Latest update is posted here.

Assembled PC Boards are here!  We got shipping confirmation for the production cases and those should be arriving in 6 days.  That just leaves final assembly, firmware installs, packing and then we ship!

We may be shipping sooner than May 1st!

The cases have arrived!  We are assembling all the pre-orders and will be shipping within two weeks.

We are proud to announce we are now shipping Myro:Air.  We have limited stock so be sure to place your order.